24350Kilometers of 188bet Live Casino.
Full length of the main line of the project line142.3Kilometers, full line design4A Chinese enterprise consortium led by 188bet International Co., Ltd., a subsidiary of 188bet Group Co., Ltd., and an Indonesian enterprise consortium have adopted a joint venture2015Year10month16Day, Indonesia China High-Speed Railway Co., Ltd. (KCIC) was incorporated in Indonesia.2017Year4month4Indonesia China 188bet Live Casino Co., Ltd. and a consortium of 188bet Live Casino contractors officially signed the general contract for the Jakarta-Bandung 188bet Live Casino project in Jakarta (EPC) Contract.2017Year5month14China Development Bank and Indonesia-China High-Speed Railway Co., Ltd. formally signed a loan agreement for the Jakarta-Bandung 188bet Live Casino project in Indonesia
2018Year6The key and control projects of the Jakarta-Bandung 188bet Live Casino line have started2018Year12month12On Japan, the first box girder of the Jakarta-Bandung 188bet Live Casino was opened4#The concrete pouring of No. 0 block of the two main piers of the Jakarta-Bandung 188bet Live Casino’s largest continuous rigid frame bridge was successfully completed
Three girder yards along the Jakarta-Bandung High-Speed Railway in Indonesia have begun to continuously erect girder
Relevant government departments and participating enterprise representatives from China and Indonesia witnessed the completion of the tunnel through video connections in Beijing and Jakarta
29
29294month30The main civil construction project of Dekarur Station, the terminal station of Jakarta-Bandung 188bet Live Casino in Indonesia, was successfully capped
2021Year5month18Indonesian President Joko goes to the Jakarta-Bandung 188bet Live Casino construction site
2021Year9month21The "first order" of China's "overall export" of high-speed rail--necessary for the construction of Jakarta-Bandung high-speed rail3.81All 10,000 tons of rails have been exported and transported.
2021Year9month29Japan, Jakarta-Bandung High-Speed Railway, Indonesia2On the Extra Large Bridge24Lian Liang Yu29All construction was completed on 9227_92381The beam channel in the No. 1 beam field.
2022Year2month18Day, the longest tunnel on the Jakarta-Bandung 188bet Live Casino——6This marks significant progress in another key control project across the entire line
2022Year4month20Day, first root500Meter-long track was successfully laid on the Jakarta-Bandung high-speed train line in Bandung County, West Java Province, Indonesia
2022Year5month25Japan, Jakarta-Bandung High-Speed Railway4Haoliang Field completed the Bandung direction one week ahead of schedule343Box beam erection task. as of5month29On Day 1, beam erection construction for the entire Jakarta-Bandung 188bet Live Casino line has been completed86.36%, creating good conditions for subsequent track laying and other construction.
The high-speed EMU and comprehensive inspection train customized for the Jakarta-Bandung 188bet Live Casino were successfully rolled off the assembly line in Qingdao
One set of high-speed EMUs and one set of comprehensive inspection trains exported from my country to Indonesia for the Jakarta-Bandung 188bet Live Casino were transported from Qingdao Port to Indonesia
This marks the cancellation of all major and difficult projects on the Jakarta-Bandung 188bet Live Casino
The high-speed EMUs and comprehensive inspection trains exported from China to the Jakarta-Bandung High-Speed Railway arrived at Tanjong Priok Port in Jakarta, Indonesia on September 1
The first traction main transformer of Jakarta-Bandung 188bet Live Casino was successfully installed at Dekarur Substation in Indonesia
2022From Jakarta-Bandung High-Speed Railway Dekarur Station to PadaLalangmarks that Indonesia’s first 188bet Live Casino with a speed of 350 kilometers per hour has entered the electrification professional core technology construction stage
11, 2022This indicates that the Jakarta-Bandung 188bet Live Casino test section has the conditions for the online operation of EMUs
The hot slip test of the catenary network in the Jakarta-Bandung 188bet Live Casino test section in Indonesia is in full swing
President Xi Jinping and Indonesian President Joko jointly observed the successful trial operation of the Jakarta-Bandung 188bet Live Casino in Bali via video link
2023Year2month15Creating favorable conditions for subsequent track laying and completion and the opening and operation of the entire line
2023Year2month27The first batch of training courses for Jakarta-Bandung 188bet Live Casino operation and maintenance personnel officially opened in Molifen City, East Java Province, Indonesia173People, focusing on training EMU drivers,OCCFour professional positions of emergency duty personnel and EMU mechanics
The track paving ceremony for the entire Jakarta-Bandung High-Speed Railway was held at Halim Station in Jakarta, Indonesia
Dekarur 4 traction substations 27
Starting from 16:00 on May 22, 2023 (17:00 Beijing time)
The Jakarta-Bandung 188bet Live Casino joint commissioning and comprehensive testing train operating speed reaches 350 kilometers per hour for the first time
2023The Jakarta-Bandung 188bet Live Casino jointly constructed by China and Indonesia is put into operation。
2023Year10month17President Xi Jinping and visiting Indonesian President Joko jointly unveiled the commercial operation of the Jakarta-Bandung 188bet Live Casino