Chapter 1 General Provisions
In accordance with national laws and regulations and the relevant regulations of 188bet Corporation (hereinafter referred to as the Corporation)
Article 2 These Measures apply to large and medium-sized railway construction projects managed by the head office (including agency construction projectsEPCInternational projects managed by the head office) 188bet mobile of corporate credit evaluation work
Article 3 The credit evaluation of the 188bet mobile enterprise (hereinafter referred to as the credit evaluation) refers to the comprehensive evaluation of the 188bet mobile enterprise’s contract performance and supervisory personnel’s performance by the construction unit organized by the head officeA、B、CLevel three.
Head office launchAImplement the personal deduction points assessment system for supervisors
Article 4 The credit evaluation of 188bet mobile enterprises shall be an evaluation period every six months3Only identify the bad behavior of the 188bet mobile company and the 188bet mobile personnelCLevel.
Article 5 The construction unit shall include matters related to the credit evaluation of the 188bet mobile enterprise into the 188bet mobile contract
Article 6 The credit evaluation work of 188bet mobile enterprises shall be fair
Chapter 2 Organization Management
Article 7 The Construction Department of the head office is responsible for supervising the management of corporate credit evaluationAThe Ministry of Industry and Electricity is responsible for reviewing the deduction points for speed limit points on high-speed railways due to engineering quality reasons
290
Article 9Construction Project188bet mobile enterprise credit evaluation full score300Points, basic points290The final score is the basic score minus the daily inspection deduction points and bad behavior deduction points10limited points).
Construction units should follow the "Guiding Opinions on Deepening the Standardized Management of Railway Construction Projects" of the Corporation (General Railway Construction [2013〕193"Implementation Measures for Performance Evaluation of Standardized Management of Railway Construction Projects" (General Railway Construction〔2014〕28012
Standard compliance evaluation refers to the evaluation of the construction of the standardized management system within six months after the 188bet mobile company enters the site10points, those who fail are0points, awarded to those who pass the test6-10201The score is the actual score divided by the 100-point system according to the standardized management performance evaluation method for construction project 188bet mobile enterprises10(reserved1decimal places).
Major bad behavior occurs within an evaluation period or2The evaluation of standardization management of 188bet mobile projects shall not be rated as qualified
The construction unit should determine the results of the standardized management performance evaluation3The evaluation results will be entered into the railway engineering management platform within a few days.
The Engineering 188bet mobile Bureau of the head office should establish a list of personnel for personal deductions and dismissal of chief supervisory engineers and supervisors
Chapter 3 Daily Inspection
Article 12 Routine inspection refers to during the railway construction process
The contract and the relevant provisions of the head office shall conduct daily inspections on the on-site 188bet mobile work of construction projects2The inspection items and frequency of each 188bet mobile bid section should be basically the same
Article 14 The construction unit shall respond to the problems discovered during the inspection1), please refer to the attachment1Point deduction standards and publication period (attachment2、3、4) to record.
Article 15 Deductions for daily inspections must be signed by two or more inspectors
Article 16 The construction unit shall complete the daily inspection after3The Railway Bureau Group Company is responsible for inputting into the railway engineering management platform
Article 17 The railway engineering quality and safety 188bet mobile agency discovers problems that meet the point deduction standards of the "Daily Inspection Point Deduction Table" during daily 188bet mobile and inspection or special 188bet mobile and inspection3Responsible for entering inspection results into the railway engineering management platform by project
Article 18: Routine inspections reveal problems with projects contracted by the 188bet mobile consortium20%Points will be deducted. Other participants in the consortium will not be deducted points.
Chapter 4 Bad Behavior
Article 19 The bad behavior of 188bet mobile enterprises and personnel refers to 188bet mobile enterprises and their 188bet mobile personnel involved in railway engineering construction activities
Article 20 Bad behaviors are classified into general bad behaviors2、3、4Identify and deduct points for bad behaviors that meet the conditions for identifying bad behaviors
Article 21 Construction projects for which the Railway Bureau Group Company is the construction unit
Article 22 The supervisory agency of the head office is supervising and inspecting
When the identification results of the construction unit and the Railway Administration Group Company 188bet mobile Station (hereinafter referred to as the 188bet mobile Station) are inconsistent
Article 23 When the relevant departments of the head office conduct various inspections on construction projects
Relevant departments of the head office should immediately refer issues that meet the conditions for identification of bad behavior to the Engineering 188bet mobile Bureau of the head office
Article 25 The construction unit shall review the bad behaviors recorded on site and the bad behaviors identified by the 188bet mobile agency received3Announcement will be made through the railway engineering management platform within the day3A public notice should be posted at the location of the project management agency of the construction unit510
It will be entered into the railway engineering management platform on the day the bad behavior is determined by the project management agency of the railway company and railway bureau group company
Article 27 The same bad behavior shall not be recorded repeatedly
Article 28 The subject of the 188bet mobile contract is a consortium
2020%Record the bad behavior of the responsible party and the consortium leader at the same time
Article 29 Major bad behavior occurs and can be identified immediately2It should be determined and submitted according to the procedures after the investigation results are determined
Article 30 The 188bet mobile enterprise and the person responsible for 188bet mobile refuse to make corrections or fail to make corrections after the bad behavior is announced
Chapter 5 Summary of Evaluation Results
Article 31 188bet mobile enterprises that have major bad behaviors in railway construction projectsCOther projects in this construction unit and other construction units are still evaluating them
Article 32: Ranking top in overall credit evaluation score10The credit rating of the 188bet mobile company isAlevel, evaluation score ranking last3The credit rating of the 188bet mobile company with major bad behavior isCThe credit evaluation level of 188bet mobile companies with other rankings isBLevel.
Only in1Only evaluated within construction projects and construction unitsBlevel, serious bad behavior will be directly rated as stipulatedCLevel.
Article 33 The 188bet mobile company is notified by the head office due to serious quality problems or other major breaches of contract in projects under construction during the evaluation period
Article 34 188bet mobile companies are responsible for speed limit points on high-speed railways caused by engineering quality
(1) Processing standards.
1.High-speed railway appears every time due to engineering quality reasons1Directly deducted from the preliminary summary score of the supervisory enterprise’s credit evaluation for the current period1.5Points.
2.The same unit appears in the same evaluation period3Responsible for completing the remediation within the determined time limitALevel; for occurrence4Responsible for speed limits at and aboveCLevel.
(2) Recognition procedures.
The meeting minutes and points deduction suggestions shall be submitted to the Construction Department of the Head Office in a letter from the Railway Bureau Group Company
The project management agency of the Railway Bureau Group Company should automatically generate and publicize the credit evaluation score of the 188bet mobile project through the railway engineering management platform3Day.
Construction projects that do not use the railway engineering management platform6It is stipulated to calculate the credit evaluation score of the 188bet mobile enterprise of this project.
The railway company summarizes the project credit evaluation results of 188bet mobile companies within the construction unit1month20Day,7month20The evaluation results were attached twice a few days ago7The credit evaluation results of the 188bet mobile projects reported should be graded and no full marks should be allowed3Home.
Article 37: The regional 188bet mobile station shall organize the credit evaluation of construction project management agencies1month20日和7month20Recently submitted a 188bet mobile report to the Engineering 188bet mobile Bureau of the head office.
Article 38 The Engineering 188bet mobile Bureau of the Corporation shall base on the evaluation results reported by the construction unit6Calculate the summary score of credit evaluation of 188bet mobile companies on the whole road
The 188bet mobile companies with the largest number of high-speed railways participating in the evaluation period are ranked first
A major or above-level production safety accident or a major or above-level quality accident occurred due to quality reasons in a project that has been completed and deliveredCLevel.
Article 40 Selection in each evaluation period20nameA The construction unit selects a chief supervisory engineer to participateA The personal deduction points and other information shall be submitted to the Engineering 188bet mobile Bureau of the head office together with the project credit evaluation results of the 188bet mobile enterprise2Those who are chief supervisory engineers or below will not participateA Selection of senior chief supervisory engineer.
The Engineering 188bet mobile Bureau evaluates the score based on the 188bet mobile bid section where the chief 188bet mobile engineer is located10famous chief supervisory engineer, rated asA The chief supervisory engineer with the fewest personal deduction points will be ranked first
The Engineering 188bet mobile Bureau jointly conducted preliminary evaluation results of the credit evaluation of 188bet mobile companiesA Published by the Construction Department of the Corporation on the Railway Construction Engineering Network5Working days, it will be announced after there is no objection.
Objections accepted shall be handled by the Construction Department of the head office in conjunction with the Ministry of Industry and Electricity
Chapter 6 Results Application
Article 42 The evaluation isA-level engineering 188bet mobile enterprises, starting from the date of announcement of the evaluation results6Given within one month1Extra points for each bid, the extra points are2Points. Rated twice in a row within one yearAlevel enterprise, increase1But it can only be used during the first evaluation period of the following yearA-level 188bet mobile enterprises can choose the bidding sections to apply for use.
Report the bonus points of the 188bet mobile company to the Industrial Management Center of the head office
Article 43 Bidding for the same batchAlevel enterprise among them1Apply for credit evaluation points for each bid. Credit evaluationA-level enterprises use bidding to increase share rights, they should submit it with the bidding documents“Supervisory Enterprise Credit Evaluation Points Statement Letter”Sealed with bid letterA-level enterprises apply for credit evaluation bonus points for different projects opened at the same timeALevel enterprise has used bonus points once.
When bidding for a consortium, the leading party isA-level enterprises can apply for approval1Extra points for each bid, but the consortium members haveClevel enterprise, no points will be added to the consortium, it will be countedA-level enterprises use bonus points once.
Article 44 The evaluation isC-level 188bet mobile enterprise, after the evaluation results are officially announced2months is the rectification period. after the rectification period10The rectification situation should be reported in writing to the Construction Department and Engineering 188bet mobile Bureau of the head officeC-level 188bet mobile companies issue railway project 188bet mobile bidding documents.
Article 45 The credit evaluation results of construction project 188bet mobile enterprises shall be used as the main basis for payment of incentive and restraint assessment fees
(1) The 188bet mobile assessment fee is the 188bet mobile contract amount (188bet mobile fee)1%, included in the bid quotation and total contract price.
The cost of the assessment period is the total 188bet mobile assessment fee divided by the number of credit evaluations of the 188bet mobile project=Total construction period for preliminary design approval (months)/6。
(3) Major bad behavior occurs in the 188bet mobile project during the evaluation period or3Those who commit the above serious bad behaviors100%In other cases, the construction unit shall specify the quota in the implementation details
Article 46: Being selected asAExtra points for each bid, the extra points are1points, starting from the next evaluation period to the first5It can only be used after the 188bet mobile project contract expires5The opportunity for bonus points for bidding is extended to the next evaluation period at the end of the contract
Article 47AAdditional points for the bidding of the first-level chief supervisory engineer will be given by the supervisory company where he is elected when he participates in the 188bet mobile bid as the chief supervisory engineer1numberAAdditional points for bidding by senior supervisory engineers are only allowed1Application for use of bids,1can only be used once1Extra points; in2The credit evaluation bonus applied for is invalid1times.
When bidding for a consortium, the leader can bid1Application for use of bidsAAdditional points for the senior chief supervisory engineer’s bid, but the consortium members haveClevel enterprise, no points will be added to the consortium, and the use will be countedALevel-level supervisory engineer’s bidding bonus1times.
The construction unit should promptly addAReport the bidding bonus points of the senior supervisory engineer to the head office's industrial management center
Article 48AMajor bad behavior occurred in the 188bet mobile section where the senior supervisory engineer worked
Article 49 The total number of personal deduction points for the chief supervisory engineer and supervisory personnel within an evaluation period reaches12At the same time, you are not allowed to engage in construction activities in railway construction projects managed by the head office within one year12Score points will be eliminated
Article 50 The credit evaluation work of railway construction project 188bet mobile shall be included in the assessment scope of the construction unit1~3The person in charge of the Railway Bureau Group Company will be deducted points according to regulations during the business performance assessment
Chapter 7 Information Management
Article 51 The construction unit is responsible for entering all supervisors of its managed projects into the railway project management platform
Article 52 The Corporation shall establish a blacklist system for railway construction 188bet mobile enterprises and supervisors
Article 53 The Industrial Management Center of the head office is responsible for management on the railway engineering management platformAlevel 188bet mobile enterprise,AAnd promptly inform the Industrial Management Center of the use of bid bonus pointsAThe Engineering 188bet mobile Bureau of the head office promptly informs the Engineering Management Center for updates
The construction unit will deduct points for individuals up to12The Engineering 188bet mobile Bureau promptly included the list of persons with personal deductions and discharged points and announced it on the railway engineering management platform
The construction unit should inquire about the main supervisory personnel proposed by the 188bet mobile company
Chapter 8 Supplementary Provisions
Article 56 The head office establishes a credit evaluation 188bet mobile and reporting mechanism for supervisory enterprises
Report hotline: Construction Department of the head office010-51844717,010-51848850(Fax); 188bet mobile Bureau of the Head Office010-51844279,010-51841289(Fax); Engineering 188bet mobile Bureau of the Head Office010-51848870,010-51842837(fax).
Article 57 The construction department of the head office is responsible for the interpretation of these regulations
Article 58 These Measures are from2018Year7month1Effective from today, Original "Measures for the Credit Evaluation of Railway Construction Project 188bet mobile Enterprises" (General Railway Construction [2014〕86) shall be abolished at the same time.
Attachment:1.Daily inspection deduction list
2.Recognition of general bad behavior records, point deduction standards and publication period
3.Identification of major bad behaviors, points deduction standards and publication period
4.Conditions for identifying major bad behavior records and publication period
5.Railway construction project 188bet mobile bad behavior identification record sheet
6.Scoring and sorting principles related to credit evaluation of 188bet mobile enterprises
7.Construction unit evaluation results